Design and construction phases of Ora Bridge located approximately 3km from the Gulu – Arua Road, including a 9.2km upgrade of the gravel approach to the bridge.

About the Project:

Supply and install portable modular single lane (minimum 5.4m wide), 39.6 single span steel bridge, Installation of ancillary works and amenities, guardrails, signs, river protection works gabions etc.

Necessary surveys and Geotechnical Investigations to aid design acceptable to UNRA

Design and construction of approximately 8km of Gravel road to Design class C Gravel in accordance with the Road Design Manual: Volume 1: Geometric Design issued by Ministry of Works and Transport

River training works 70m upstream and downstream including gabion/ rip rap protection to embankments;

 

Reconstruction of washed out and failed Ora Bridge
Location:
Okollo – Anyiribu Road
District:
ARUA DISTRICT
Bridge Form:
Steel Bridge supported on reinforced concrete abutments
Span:
25m
Project Design Year: