Kasese

Consultancy Services for Design Review and Construction Supervision for Selected Infrastructure Sub-projects in Cluster 7 (USMID-AF) UGANDA

About the Project:

The Project involves Design Review & Construction Supervision for the upgrading to Bitumen standard (Asphalt) with provision of mechanically stabilised sub-base, crushed aggregate base, reinstatement of road sides and cross drainage features and Bridges among others.

The projects roads within Kasese Municipality include;

  • Rwenzori Road – 1.35Km
  • Bus Circular Road – 0.45Km
  • Third Street – 0.76Km
  • Kitalikibi Road – 0.42Km
  • Park Rise Road – 0.18Km
  • Stanley Road – 0.43Km
  • Margherita Road – 0.45Km
Selected Infrastructure Sub-projects in Cluster 7 (USMID-AF) UGANDA
Role:
Design Review and Supervising Consultant
Location:
Kasese in WESTERN UGANDA
Client:
Kasese Municipal Council
Total Road Lengths:
9.0 Km
Completion Year:
2025